Project 2013 Introduction
Project 2013
Lesson 1 – Learning Project Basics
NOTE To mark multiple days in the currently displayed calendar at the same time, drag to select consecutive days. To select non- consecutive days, hold the [Ctrl] key, click the desired days, and then release the [Ctrl] key.
Procedures
1. Select the Project tab on the Ribbon. 2. Click the Change working time icon in the Properties group. 3. Display the month in the calendar in which you want to add the nonworking day. 4. Select the day on the calendar you want to add as nonworking. 5. In the Exceptions tab type the name of the holiday. 6. Press the tab key. The selected day from the calendar is automatically added. You can change the date manually, if needed 7. Select OK .
Step-by-Step
We will add the Federal holidays to the end of the current year. Add a nonworking day.
Steps
Practice Data
1. Select the Change Working Time icon. The Change Working Time dialog box opens with the current project calendar template displayed in the For box. 3. Display the month in the calendar in which you want to add the nonworking day. The desired month appears. 4. Select the day on the calendar you want to add as nonworking. The desired day is selected.
Click
Scroll as necessary to display July 2016.
Select the 4 th and the 5 th on the calendar.