Lesson 1 – Learning Project Basics
Project 2013
Steps
Practice Data
12. Select OK .
Click
.
The Change Working Time dialog box closes and the options are saved.
A DDING A N ONWORKING D AY
Discussion
By default, the project calendar defines the standard working days (Monday through Friday) and nonworking days (Saturday and Sunday) for a project. The default calendar has no holidays, so you must mark the appropriate holidays as nonworking days. It is very important to mark all applicable nonworking days as durations are calculated according to this calendar. In any view, nonworking days are identified with gray shading.
You can enter the nonworking days by directly opening the Change Working Time dialog box.
The Change Working Time dialog box