Project 2013 Introduction

Project 2013

Lesson 3 – Working with Tasks

currently selected field. Using the entry bar, you can select the words or characters you want to edit. Using in-cell editing, you simply select the field and edit the entry in the field as desired.

Procedures

1. Switch to the Gantt Chart view. 2. Select the field containing the entry you want to replace. 3. Enter the new entry. 4. Press [Enter] .

5. To edit an entry in the entry bar, select the field containing the entry and double- click on the text to edit. NOTE: To add the entry bar, select File\Options\Display and select Entry bar. 6. Select the text you want to edit in the entry bar within the Task Information Window. 7. Enter the new text. 8. Press [Enter] . 9. To use in-cell editing, select the field containing the entry. 10. Press [F2] to put the field in edit mode. 11. Edit the entry as desired. 12. Press [Enter] .

Step-by-Step

Edit tasks.

Steps

Practice Data

1. Select the field containing the entry you want to replace. The desired field is selected.

Click the Duration field for the Request Bids task.

2. Enter the new entry.

Type 1w.

The new entry appears in the field and in the entry bar.

3. Press [Enter] .

Press [Enter].

The new entry is entered and the Gantt chart is updated.