Project 2013 Introduction

Project 2013

Lesson 3 – Working with Tasks

Steps

Practice Data

8. Enter a task name.

Type Develop Blueprints.

The task name is entered.

9. Press [ Tab ] to get to the Task duration.

Press [Tab].

The task is entered; a bar appears on the Gantt chart for the task.

10. Enter the Task duration.

Type 1w

The desired duration appears in the Duration field. Note: No Gantt Bar appears because this task is manually scheduled with no fix duration or StartDate. 11. Select the next empty field in the Task Name column.

Click in the next empty field in the Task Name column.

A border appears around the Task Name field and the mouse pointer changes into a cross.

12. Enter a task name

Type Obtain Bids.

The task name is entered.

13. Press [ Tab ] to get to the Task duration.

Press [Tab].

The task is entered; a bar appears on the Gantt chart for the task.

14. Enter the Task duration .

Type 1w

The desired duration appears in the Duration field.

15. Click on the Task Tab.

Click

.

This displays the Task ribbon.

16. Click the Inactivate icon from the Schedule group. The task becomes inactive.

Click

.

Close the file without saving the changes.