Project 2013 Introduction

Lesson 3 – Working with Tasks

Project 2013

E NTERING A M ILESTONE T ASK

Discussion

A milestone task indicates that a goal should be reached in a particular phase of a project, such as “End Planning”. Since a milestone task marks an event or progress in your project, it is not allotted a specific duration. Instead, you designate a task as a milestone by entering a duration of zero days for the task. A milestone task is shown on the Gantt chart as a filled diamond shape with the date of the task beside it. You enter a milestone task just as you do other tasks.

Entering a milestone task

NOTE You can also set a milestone using the Project Guide. From the Tasks pane, select the List the tasks in the project link, select the task you want to mark as a milestone, and then click the Make selected task a milestone check box in the List Tasks pane.

Procedures

1. Switch to the Gantt Chart view. 2. Select the field in which you want to enter the milestone task. 3. Enter a name for the milestone task. 4. Select the Duration field. 5. Enter a duration of 0 days for the milestone task. 6. Press [Enter] .

Page 56

OFFICEPRO, Inc.

Made with FlippingBook HTML5