Project 2013 Intermediate

Lesson 5 – Working with Baselines

Project 2013

Steps

Practice Data

3. Select the Set Baseline… option. The Set Baseline window opens.

Click

.

4. If necessary, select For: Entire project option. The Entire project option is selected.

Click

, if

necessary.

5. Click the OK button.

Click

.

The current project baseline is updated.

6. Click Yes to overwrite the old baseline.

Click

.

All of the Tracking Gantt bars now line up.

U PDATING T ASKS IN A B ASELINE

Discussion

When you save a baseline, the default option makes a copy of the baseline for the entire project; however, you can also save a baseline of selected tasks. Saving a baseline of selected tasks is helpful when you have saved a baseline of the entire project and then realize you need to adjust certain incorrect task information. You can revise the tasks and then update the original baseline for those tasks only.

In addition, during the life of the project you may need to add tasks after the baseline has been saved. You can select those new tasks and add them to your original plan by updating the original baseline.

Page 100