Lesson 5 – Working with Baselines
Interim Plans are save the same way as Interim Baselines. In the Set Baseline dialog box, you can specify in which of the ten fields you want to hold the saved data. If you select fields that already contain data, the new data overwrites the existing data.
Viewing interim plan data
Procedures
1. Switch to the Gantt Chart view.
2. Select the Project tab.
3. Click the
button.
4. Select the
command.
5. Select the Save interim plan option.
6. Select the Copy list.
7. Select the fields you want to copy.
8. Select the Into list.
9. Select the fields into which you want to copy the selected fields.
10. Select the Entire project option.
11. Select
.