Project 2013 Intermediate

Lesson 5 – Working with Baselines

Project 2013

Step-by-Step

Save a project interim plan.

If necessary, switch to the Gantt Chart view.

Apply the Variance table to the view and drag the split bar as far right as possible. Constrain the 3 Develop Blueprints task so that it starts no earlier than 6/17/16 . Notice that there is now a variance for all the tasks affected by the change.

Steps

Practice Data

1. Select the Project tab.

Click

.

The Project ribbon is visible.

2. Click the Set Baseline button.

The Set Baseline submenu appears.

Select

.

3. Choose the Set Baseline... from the submenu. The Set Baseline dialog box opens. 4. Select the Set interim plan option. The Set interim plan option is selected.

Click

.

Click

.

5. Select the Copy list.

Click Copy

.

A list of options appears.

6. Select the fields you want to copy. The desired fields appear in the Copy box.

Click Scheduled Start/Finish.

7. Select the Into list.

Click Into

.

A list of options appears.

8. Select the fields into which you want to copy the selected fields. The destination fields appear in the Into box.

Click Start1/Finish1.

9. Select the Entire project option.

Click

, if

The Entire project option is selected.

necessary.