Lesson 5 – Working with Baselines
Steps
Practice Data
10. Select OK .
Click
The Set Baseline dialog box closes and the interim plan is saved.
Add the Start1 column to the left of the Baseline Start column and the Finish1 column to the left of the Baseline Finish column in the current view. Notice the difference in the dates due to the seven day variance.
C LEARING A B ASELINE
Discussion
After saving baseline data, you may decide that you do not want this data used for comparison purposes. If desired, you can clear the baseline and save it at a later time. You may also want to clear baseline data if you plan to use a completed project as the basis for future projects.
You can clear baseline information for the entire project or for a particular task. In addition, you can clear the dates saved in an interim plan as desired.
The Clear Baseline dialog box
Procedures
1. Switch to the Gantt Chart view.
2. Select the task for which you want to clear the baseline.
3. Select the Project tab.