Lesson 6 – Tracking Your Progress
Project 2013
NOTE In addition to marking a task 100% complete, you can use the buttons on the Schedule group of the Task ribbon to record that a task is 25%, 50% and 75% complete. You can also remove recorded progress by marking a task as 0% complete.
Procedures
1. Switch to the Gantt Chart view. 2. Select the task you want to mark as complete.
3. Click the 100% Complete button
on the Task ribbon, Schedule group.
Step-by-Step
From the Student Data directory, open HOUSE15.MPP . Update a completed task.
If necessary, switch to the Gantt Chart view.
Display the Task ribbon.
Steps
Practice Data
1. Select the task you want to mark as complete. The desired task is selected. 2. Click the 100% Complete button from the Schedule group on the Task ribbon. The task is marked complete and the Act. Start and Act. Finish fields are completed.
Click the 2 Conduct Survey task, if necessary.
Click
.
Notice that a checkmark appears in the Indicators field for the task and the progress bar extends the full length of the task bar.
Page 116