Project 2013 Intermediate

Lesson 6 – Tracking Your Progress

Project 2013

NOTE

A dotted line appears in the Gantt chart for the date set in the Current date box in the Project Information dialog box. If you deselect the Updating task status updates resource status option on the Calculation page of the Options dialog box, Microsoft Project will not enter values in the Actual Work field when you enter a percent complete or change the actual or remaining duration.

Procedures

1. Select the Project tab. 2. Select the Project Information icon in the Properties group. 3. Select the text in the Status date box. 4. Enter the desired status date.

5. Select

.

Step-by-Step

Set the status date.

Steps

Practice Data

1. Select the Project tab.

Click

.

The Project ribbon appears.

2. Click the Project Information icon. The Project Information dialog box opens.

Click

.

3. Select the text in the Status date box. The text is selected. 4. Enter the desired status date. The status date appears in the Status date box.

Drag to select the text NA in the Status date box.

Type 6/16/16