Project 2013 Intermediate

Lesson 6 – Tracking Your Progress

Project 2013

Updating a task on schedule

NOTE

A Planning Wizard dialog box opens if the time span includes a task with a constraint or deadline date. You can update multiple tasks on schedule by selecting the tasks before you click the Update as Scheduled button.

Procedures

1. Switch to the Gantt Chart view. 2. Select the Task ribbon.

3. Click the Update as Mark on Track button

in the Schedule

group.

Step-by-Step

Update a task on schedule.

If necessary, switch to the Gantt Chart view. Apply the Tracking table, drag the split bar as far right as possible.

Note: The status date for this project is set to 6/16/16. .

Page 120

OFFICEPRO, Inc.

Made with FlippingBook - Online magazine maker