Lesson 6 – Tracking Your Progress
Project 2013
Updating a task on schedule
NOTE
A Planning Wizard dialog box opens if the time span includes a task with a constraint or deadline date. You can update multiple tasks on schedule by selecting the tasks before you click the Update as Scheduled button.
Procedures
1. Switch to the Gantt Chart view. 2. Select the Task ribbon.
3. Click the Update as Mark on Track button
in the Schedule
group.
Step-by-Step
Update a task on schedule.
If necessary, switch to the Gantt Chart view. Apply the Tracking table, drag the split bar as far right as possible.
Note: The status date for this project is set to 6/16/16. .