Lesson 6 – Tracking Your Progress

Project 2013

Updating a task not on schedule

NOTE

If a task with a constraint or deadline date is impacted by a task that is not on schedule, a Planning Wizard dialog box will open. You then need to select an option in the dialog box and adjust the schedule as necessary.

Procedures

1. Switch to the Gantt Chart view. 2. Apply the Tracking table. 3. Select the Act. Start field for the desired task. 4. Enter the actual start date for the task. 5. Select the Act. Finish field for the desired task. 6. Enter the actual finish date for the task. 7. Press [Enter] .

Step-by-Step

Update a task not on schedule.