Lesson 6 – Tracking Your Progress
Entering actual work values
Procedures
1. Switch to the Task Usage view. 2. Apply the Work table. 3. To enter actual work completed, select the Actual field for the task or for the individual resource assigned to the task you want to update. 4. Enter the total number of hours of work completed on the task or the hours of work completed by the individual resource. 5. Press [Enter] . 6. To enter the remaining work, select the Remaining field for the task or for the individual resource assigned to the task you want to update. 7. Enter the total number of hours of work completed on the task or the hours of work completed by the individual resource. 8. Press [Enter] .
Step-by-Step
Enter completed and remaining work values.