Project 2013 Intermediate

Lesson 6 – Tracking Your Progress

Project 2013

Switch to the Task Usage view, apply the Work table, and drag the split bar as far right as possible. Double-click the right border of the Task Name column to view the entire field.

For 10 Select Subcontractors task, the Superintendent has performed a total of 32 hours of work. However, due to a scheduling problem, you need to schedule this resource to perform 12 more hours of work that was originally scheduled for the Superintendent resource.

Steps

Practice Data

1. To enter actual work completed,

Click the Actual field for the Superintendent resource assigned to the 10 Select Subcontractors task.

select the Actual field for the task or for the individual resource assigned to the task you want to update. The desired Actual field is selected.

2. Enter the total number of hours of work completed on the task or the hours of work completed by the individual resource. The total number of hours of work completed is entered..

Type 44.

3. Press [Enter] .

Press [Enter].

The appropriate fields are updated.

4. To enter the remaining work, select the Remaining field for the task or for the individual resource assigned to

Click the Remaining field for the Superintendent resource assigned to the 10 Select Subcontractors task.

the task you want to update. The desired Remaining field is selected.

5. Enter the total number of hours of work completed on the task or the hours of work completed by the individual resource. The total number of hours of work remaining is entered..

Type 12.

6. Press [Enter] .

Press [Enter].

The value is entered and the appropriate fields are updated.