Project 2013 Intermediate
Project 2013
Lesson 6 – Tracking Your Progress
7. Continue to change the work values as desired.
Step-by-Step
Enter timephased work values.
Switch to the Task Usage view and apply the Work table. Select the Task Usage Tools Format tab. Check Actual Work checkbox in the Details group. If necessary, drag the split bar so that the timephased details start to the right of the Work field in the table.
Select the 18 Frame House task and use the Scroll To Task button to scroll to the work assignment.
Steps
Practice Data
1. Select the Act. Work field for the
Scroll as necessary and click the Act. Work field in the first T column under the 24h for the Carpenter resource (for the date 8/16/16 )
assigned resource for which you want to enter timephased work values. The desired Act. Work field for the resource is selected.
2. Enter the desired value.
Type 12
The desired value is entered.
3. Press [Enter] .
Press [Enter].
The actual work value for the resource is entered and added to the actual work value for the task. 4. Continue to change the work values as desired. The contour of the work assignment changes accordingly.
Enter 28 hours of actual work for the carpenter for Wednesday thru Friday.
Practice the Concept: Scroll to the week of Aug 21, 16 . For the carpenter, enter 28 hours of actual work for Monday. Enter 20 hours of actual work for Tuesday, which finishes the task.