Lesson 6 – Tracking Your Progress
Step-by-Step
Reschedule uncompleted work.
Switch to the Gantt Chart view and apply the Entry table. Select the 19 Frame Garage task and mark it as 50% complete. Drag the split bar to the left and scroll to view the task bar for the task.
The Carpenter has jury duty and probably cannot continue the rest of the work until after 9/2/16. You need to reschedule the remainder of the task.
Steps
Practice Data
1. To reschedule the uncompleted work for specific tasks, select the desired tasks. The tasks are selected.
Click the 19 Frame Garage task, if necessary.
2. Select the Project ribbon. The Project ribbon appears.
Click
.
3. Select the Update Project command from the Status group. The Update Project dialog box opens. 4. Select the Reschedule uncompleted work to start after option. The Reschedule uncompleted work to start after option is selected. Reschedule uncompleted work to start after box. The selected date appears in the Reschedule uncompleted work to start after box. 6. Select the Selected tasks option to reschedule work for selected tasks only. The Selected tasks option is selected. 5. Type the desired date in the
Click
.
Click Reschedule uncompleted work to start after.
Type 9/3/16.
Click
Selected tasks.