Project 2013 Intermediate
Lesson 6 – Tracking Your Progress
Project 2013
Steps
Practice Data
7. Select OK .
Click
.
The Update Project dialog box closes and uncompleted work before the selected date is rescheduled.
The 19 Frame Garage task is split, with the uncompleted work rescheduled to start after 9/3/16. The duration of 3 days remains unchanged.
The carpenter was able to return early and finish framing the garage by 9/6/16. Open the Project Information dialog box and change the status date to 9/8/16 . Mark the Frame Garage task as 100% complete. Notice that the progress bar indicates the work was completed after the rescheduled date of 9/8/16. Use the Undo button on the Quick Access toolbar to undo marking the task complete.
Drag the right half of the task bar to the left. The split bar becomes whole again. Mark as 100% Complete.
A PPLYING P ROGRESS L INES
Discussion
Microsoft Project provides many ways to view the progress of a project. In addition to the different views available, you can display progress lines on the Gantt chart. Progress lines connect tasks in progress and contain peaks that illustrate whether or not a task is behind or ahead of schedule. If a peak points to the left, then the task is behind schedule; if a peak points to the right, then the task is ahead of schedule. When you apply progress lines, you can display them as of the current date or the status date entered in the Project Information dialog box. The project status date is any date you specify for checking progress. You can also display progress lines on particular dates and at recurring intervals. In addition, you can display progress lines in relation to the actual plan or the baseline plan.