Lesson 6 – Tracking Your Progress
Notice that the progress line appears on the status date of 7/10/16 . The peak points fall on the line, indicating that everything is on schedule.
Practice the Concept: Change the status date to 8/19/16. The peaks point to the left, indicating that the 13 Dig Foundation was behind schedule.
V IEWING S UMMARY I NFORMATION
Discussion
As you work on your project, you can quickly view summary information in the Project Statistics dialog box. This dialog box is split into three different areas. The top area of the dialog box shows a comparison of the current, baseline, actual, and variance information for a project’s start and finish dates. The middle area displays the current, baseline, actual, and remaining information for a project’s total duration, work, and cost. The area at the very bottom of the dialog box, in the far left corner, displays the percentage complete for duration and work.
The Project Statistics dialog box
Procedures
1. Select the Project menu. 2. Select the Project Information command. 3. Select Statistics . 4. Select Close when you have finished viewing the summary information.