Project 2013 Intermediate
Lesson 6 – Tracking Your Progress
Project 2013
Step-by-Step
Apply progress lines.
If necessary, switch to the Gantt Chart view.
Check how your project was progressing on July 10, 2016. Open the Project Information dialog box and enter a status date for the project of 7/10/16 . Scroll to view the Gantt bars for tasks 7 and 8.
Steps
Practice Data
1. Select the Gantt Chart Tools menu. The Gantt Chart Tools ribbon appears.
Click
.
2. Select the Gridlines icon. The submenu appears.
Select
.
3. Click the Progress Lines command. The Progress Lines dialog box opens. 4. Select the Dates and Intervals tab. The Dates and Intervals page appears.
Click
.
Click the Dates and Intervals tab, if necessary.
5. Select the Display option.
Click Display: option.
The Always display current progress line option is selected.
6. Select the At project status date or At current date option. The desired option is selected. 7. Continue to select options as desired. The desired options are selected.
Click At project status date , if necessary.
Click the Baseline plan option under Display progress lines in relation to.
8. Select OK .
Click
.
The Progress Lines dialog box closes and the progress lines are applied accordingly.