Project 2013 Intermediate
Project 2013
Lesson 1 – Working with Calendars
Steps
Practice Data
1. Double-click the resource for which you want to change the availability. The Resource Information dialog box opens.
Double-click the 4 Plumber resource.
2. Select the General tab.
Click
.
The General page appears.
3. Select the first Available From field in the Resource Availability table. The first Available From field is selected and a down arrow, indicating a list, appears in the field. 4. Type the start date for the first time period. The date appears in the Available From field and in the entry bar under Resource Availability .
Click in the first Available From field.
Type 9/4/16.
5. Press [Enter] .
Press [Enter].
The date is entered into the Available From field.
6. Enter the end date for the first time period in the Available To field. The desired date appears in the Available To field.
Type 10/31/16.
7. Select the Units field.
Click in the first Units field
The Units field is selected.
8. Enter the units available for the resource during the specified time frame. The units appear in the Units field. 9. Continue to specify the resource’s availability as necessary. The resource’s availability is entered.
Click Units to 200% , if necessary
Follow the instructions shown below the table before continuing on to the next step
10. Select OK .
Click
The Resource Information dialog box closes and the resource’s availability is changed.
OFFICEPRO, Inc.
Page 9
Made with FlippingBook - Online magazine maker