Project 2013 Intermediate
Lesson 1 – Working with Calendars
Project 2013
Changing a resource's availability over time
Procedures
1. Switch to the Resource Sheet view.
2. Double-click the resource for which you want to change the availability.
3. Select the General tab.
4. Select the first Available From field in the Resource Availability table.
5. Type the start date for the first time period.
6. Press [Enter] .
7. Enter the end date for the first time period in the Available To field.
8. Select the Units field.
9. Enter the units available for the resource during the specified time frame.
10. Continue to specify the resource’s availability as necessary.
11. Select
.
Step-by-Step
Change a resource’s availability over time.
Switch to the Resource Sheet view. Notice that 200% appears in the Max. Units field for the 4 Plumber resource.