Lesson 1 – Working with Calendars
Project 2013
NOTE
You can delete a calendar using the Organizer dialog box. You can open this dialog box by selecting the dropdown on any of the views, select More Views... and the Organizer command. On the Calendars page, select the calendar you want to delete in the right pane and use the Delete button to delete the calendar.
Procedures
1. Select the Project ribbon.
2. Select the Change Working Time command.
3. Select
. Enter the name of the new base calendar.
4. Select the Create new base calendar or Make a copy of < calendar name >
calendar option.
5. Select the Make a copy of
6. Select the calendar you want to copy.
7. Select
.
8. Modify the new base calendar as desired.
9. Select
.
Step-by-Step
Create a base calendar.
Steps
Practice Data
1. Select the Project ribbon. The Project ribbon appears.
Click
.
2. Select the Change Working Time command.
The Change Working Time dialog box opens.
Click
...