Lesson 1 – Working with Calendars
Steps
Practice Data
3. Select Create New Calendar…
Click
The Create New Base Calendar dialog box opens with the text in the Name box selected. 4. Select the Create new base calendar or Make a copy of < calendar name > calendar option. The desired option is selected. 5. Select the Make a copy of
.
Click
Make a copy of
< calendar name > calendar , if necessary.
Click the next to the Make a copy of option.
Click Standard, if necessary.
appears in the Make a copy of
7. Enter the name of the new base calendar.
Type Site Workers1.
The name appears in the Name box.
8. Select OK .
Click
The Create New Base Calendar dialog box closes and the new base calendar appears in the Change Working Time dialog box.
9. Modify the new base calendar as desired. The base calendar is modified as desired.
Follow the instructions shown below the table before continuing on to the next step
10. Select OK .
Click
The Change Working Time dialog box closes and the changes to the base calendar are saved.
Scroll to view the calendar for September 2016 and mark September 6-9 as an exception named Training.
Return to the table and continue on to the next step (step 10).
Practice the Concept: Create a new base calendar called Landscaping .