Lesson 1 – Working with Calendars

Project 2013

Steps

Practice Data

7. Select OK .

Click

The Resource Information dialog box closes and the base calendar is assigned to the resource.

Switch to the Gantt Chart view and point to the task bar for the 19 Install Roof task again. Notice that the Install Roof task, to which the Roofer resource is assigned, is now scheduled to end on Fri 9/14/16 . The change occurred since the week of September 6-9, 2016 is nonworking time on the Site Workers1 base calendar. Note other tasks for the project will still occur.

Practice the Concept: Assign the Site Worker 1 base calendar to the 1 Laborer resource.

A SSIGNING A B ASE C ALENDAR TO A P ROJECT

Discussion

If the default project calendar does not meet the needs of your project, you can create a new project calendar. To create a new project calendar, you need to create a base calendar to reflect working and nonworking time specific to your project. Then, you need to assign the new base calendar to your project using the Project Information dialog box.

If you need to use a new project calendar, you should do so before you enter project information.