Lesson 1 – Working with Calendars

NOTE

In order to see the non-working time on the Gantt Chart you must change the calendar assigned to non-working time. Double click on the timescale in the Gantt chart. Select the Non-working time tab and select the new project calendar.

Procedures

1. Select the Project ribbon.

2. Select the

button.

3. Select the Calendar list.

4. Select the calendar you want to assign to the project.

5. Select

.

Step-by-Step

Assign a base calendar to a project.

Steps

Practice Data

1. Select the Project tab.

Click

.

The Project ribbon appears.

2. Select the Project Information command.

The Project Information dialog box opens.

Click

3. Select the Calendar list.

Click Calendar

A list of available calendars appears.

4. Select the calendar you want to assign to the project. The selected calendar appears in the Calendar box.

Click Site Workers1