Project 2013 Intermediate
Project 2013
Lesson 3 - Assigning Costs
Practice the Concept: Complete the rate information for the following work resources. It is not necessary to type the currency symbol, decimal point or decimals. In addition, you do not need to type the /hr since hours is the default standard unit.
ID
Resource Name
Std.Rate
16
Backhoe Operator
$25.00/hr
17
Superintendent
$35.00/hr
18
Phone Technician
$30.00/hr
19
Cable Specialist
$18.00/hr
Filter for Resources - Material and enter the rate information for the following resources:
ID
Resource Name
Material Label
Std.Rate
21
Tile
Square feet
$4.00
22
Concrete
yards
$80.00
23
Insulation
square feet
$2.00
24
Drywall
sheets
$8.00
Please check the cost of the project and see that it is now: $72,408.
A SSIGNING O VERTIME R ATES
Discussion
You can enter an overtime rate for a work resource to calculate costs if overtime work is assigned to the resource. Overtime must be assigned to a task; it is not automatically calculated for work over 40 hours. If a resource is paid the same amount for both regular and overtime hours worked, you must enter the standard rate in the Ovt. Rate field, or the overtime hours are calculated at the zero default rate. When you enter the overtime rate, you must enter the dollar amount followed by a forward slash (/) and the unit of time. The unit of time is only necessary if the rate is not hourly, which is the default.
Overtime rates only apply to work resources; therefore, this field is not available for material resources.