Lesson 3 – Assigning Costs

Project 2013

Procedures

1. Switch to the Resource Sheet view. 2. Select the Ovt. Rate field for the desired resource. 3. Enter the overtime rate and if applicable, include a forward slash (/) and the unit of time. 4. Press [Enter] .

Step-by-Step

Assign overtime rates.

If necessary, switch to the Resource Sheet view and remove any filters.

Steps

Practice Data

1. Select the Ovt. Rate field for the desired resource. The Ovt. Rate field for the desired resource is selected.

Click the Ovt. Rate field for the 16 Backhoe Operator resource

2. Enter the overtime rate and, if

Type 37.5

applicable, include a forward slash (/) and the unit of time. The rate appears in the Ovt. Rate field.

3. Press [Enter] .

Press [Enter]

The overtime rate and unit appear in the Ovt. Rate field for the selected resource.

Practice the Concept: Assign the following overtime rates to the work resources listed: