Project 2013 Intermediate

Lesson 3 – Assigning Costs

Project 2013

6. Enter the cost per use of the resource.

7. Select

.

Step-by-Step

Assign a cost per-use to a resource.

If necessary, switch to the Resource Sheet view.

Split the window to display a combination view.

Steps

Practice Data

1. Select the resource in the top pane to which you want to assign a per-use cost.

Click the 5 Surveyor resource.

The resource is selected and the bottom pane changes to display information about the selected resource.

2. Select the value in the Per use field in the bottom pane. The value is selected. 3. Enter the cost per use of the resource. The cost per use amount appears in the Per use field for the selected resource.

Drag to select the value in the Per use field in the bottom pane.

Type 50.

4. Select OK .

Click

.

The cost per use is assigned to the selected resource.

Practice the Concept: Assign a cost per-use of $100 to the 7 Architect resource and a cost per-use of $125 to the 13 Windows resource.

Page 58