Project 2013 Intermediate
Project 2013
Lesson 3 - Assigning Costs
Procedures
1. Switch to the Resource Sheet view.
2. Select the resource for which you want to enter a code.
3. Select the Code field.
4. Enter the desired code for the desired resource.
Step-by-Step
Assign resource codes.
If necessary, switch to the Resource Sheet view
Steps
Practice Data
1. Select the resource in the top pane for which you want to enter a code. The resource is selected e.
Scroll as necessary and click the 16 Backhoe Operator resource.
2. Select the Code field
Click in the Code field.
The bottom pane is activated and the insertion point appears in the Code field.
3. Enter the desired code for the resource.
Type POM880.
The desired code appears in the Code field for the selected resource.
Practice the Concept: Assign the following codes to the remaining resources:
ID
Resource Name
Code
17
Superintendent
M654321
18
Phone Technician
PO7788
19
Cable Specialist
PO7900
23
Insulation
POM573
24
Drywall
POM300
OFFICEPRO, Inc.