Lesson 3 - Assigning Costs
E XERCISE
A SSIGNING C OSTS
Task
Include resource costs and other information in your project.
1. Open Rooms9 . 2. Switch to the Resource Sheet view and split the window. 3. Enter the following information:
ID
Resource
Standard Rate
Overtime Rate
Resource Code
9
Carpet Layer
$20.00
$30.00
PO8723
10
Electrician
$30.00
$45.00
Local 721
Computer Technician
11
$35.00
$52.50
PO9035
12
Computers
$875
POM2948
13
Carpet
$3
POM1204
14
Inspection Fees
COM100
15
Permit Fees
COM101
4. Assign a cost per use of $150.00 to the 1 Architect resource. 5. Change the accrual method for the Architect resource to Start . 6. Remove the split. 7. Create a resource rate table (letter B ) for the 11 Computer Technician resource. Enter a standard rate of $40.00 and an overtime rate of $60.00 . 8. Switch to the Resource Usage view and assign the rate table B to the Install Computers task under the 11 Computer Technician resource. 9. Switch to the Gantt Chart view and split the window. Apply the Task Form to the bottom pane. 10. Assign the Board Room Furniture material resource, which has a fixed cost of $25,000 , to the 14 Install Board Room Furniture task. Assign the Computer Room Furniture material resource, which has a fixed cost of $20,000 , to the 21