Project 2013 Intermediate
Lesson 3 – Assigning Costs
Project 2013
Install Computer Room Furniture task. Finally, assign the Light Fixtures material resource, which has a fixed cost of $2,000 , to the 11 Install Light Fixtures task. 11. Remove the split. 12. View the task costs.
13. Assign a fixed cost of $1,500 to the 12 Install Curtains task. 14. Switch to the Resource Sheet view and view the table costs.
Resource Sheet
15. Close the file without saving the changes.