Lesson 4 – Working with the Critical Path

Viewing slack

NOTE

To change the default amount of slack time for critical tasks, open the Options dialog box by selecting the File tab and the Options command. Then, select the Advanced section, Calculation options for this project and change the slack time in the Tasks are critical if slack is less than or equal to ____ days spin box. You may want to be sure you are viewing the most recent calculations of slack time by pressing the [F9] key to force calculation.

Procedures

1. Select the View tab.