Project 2013 Intermediate
Lesson 4 – Working with the Critical Path
Project 2013
2. Click the
command in the Data group
3. Select Schedule .
Step-by-Step
View slack.
Drag the split bar as far to the right as possible.
Steps
Practice Data
1. Select the View tab.
Click
.
The View ribbon appears.
2. Click the Tables button in the Data group. The Table submenu appears.
Click
3. Select the Schedule table.
Click
.
The format of the view changes to display the Schedule table, which contains the Free Slack and Total Slack columns.
Scroll as necessary to view the Free Slack and Total Slack columns. Notice that most of the tasks and subtasks for 11 Build Structure and 24 Build Infrastructure have free slack amounts of 0 days , indicating that they are tasks on the critical path.
Notice that the 4 Draft Proposal task has a total estimated slack amount of 1 day ; this is the amount by which the task can slip and still meets it deadline date. View the 6 Request Permits task and notice the total slack amount is 17.5 days. Task 8 Obtain Bids has 17.5 days of free slack. This is because task 9 Select Subcontractors has a constraint.
Page 86