Project 2016 - Introduction
Lesson – Working with Calendars
Project 2016
Modifying an individual resource work hours
NOTE To mark multiple days in the same calendar as nonworking time or change the working hours for those days, drag to select consecutive days or hold the [Ctrl] key and click the desired non-consecutive days before you select the Nonworking time or Nondefault working time option on the Working Time page in the Resource Information dialog box. If you change a resource’s start time to a time earlier than the task start time (either the default or the one set by you), Microsoft Project will ignore the work hours before the task start time and the task duration will be impacted.
Procedures
1. Switch to the Resource Sheet view.
2. Double-click the resource with the calendar you want to change.
3. Click the
button.
Page 130