Project 2016 - Introduction
Project 2016
Lesson – Working with Calendars
4. Select the Working Week tab.
5. Click the Detail… button.
6. Select the dates or days of the week you want to change.
7. Select the Use default , Nonworking time, or Nondefault working time option.
8. If setting Nondefault working hours, select the time you want to change in the
From or To column.
9. Enter the new time.
10. Continue to make changes in the From and To columns if applicable.
11. Select
.
12. Select
.
13. Select
.
Step-by-Step
From the Student Data directory, open HOUSE7.MPP . Modify a calendar for an individual resource.
In the Gantt Chart view, scroll to the week of Jul 23, ‘18 .
Notice that the Superintendent resource is scheduled to work on the 9 Select Subcontractors task, which has a duration of one week. Point to the Gantt bar for the task and view the start and finish dates to see that the task is scheduled from Monday through Friday for five working days. Switch to the Resource Sheet view.
Steps
Practice Data
1. Double-click the resource with the calendar you want to change. The Resource Information dialog box opens.
Double-click the 17 Superintendent resource.