Project 2016 - Introduction

Lesson – Working with Calendars

Project 2016

Steps

Practice Data

2. Select the Change Working Time… button. The Change Working Time dialog box appears.

Click

.

3. Select the Work Weeks tab.

Click

.

The Work Weeks sheet appears.

4. Select the Details… button.

Click

.

The Details for [Default] dialog box opens.

5. Select the dates or days of the week that you want to change. The dates or days of the week are selected. 6. Select the option under Set working times for this work week . The option is selected. 7. If setting nondefault working hours, select the time you want to change in the From or To column. The time is selected.

Drag to select Monday through Friday .

Click Set day(s) to these specific working times: Drag to select the time in the first From box, if necessary.

8. Enter the new time.

Type 8:30 AM in the first From box .

The new time replaces the original time.

Type 2:00 PM in the first To box. Type 3:00 PM in the second From box and 8:30 PM in the second To box.

9. Continue to make changes in the From and To columns as desired. The changes are made.

10. Select OK .

Click

The Details dialog box closes and the Change Working Time dialog box is still open.

11. Select OK .

Click

The Change Working Time dialog box closes and the Resource Information dialog box appears.