Project 2016 - Introduction

Lesson – Working with Calendars

Project 2016

open the Resource Information dialog box for the resource and view availability on the General page.

Changing a resource's availability over time

Procedures

1. Switch to the Resource Sheet view.

2. Double-click the resource for which you want to change the availability.

3. Select the General tab.

4. Select the first Available From field in the Resource Availability table.

5. Type the start date for the first time period.

6. Press [Enter] .

7. Enter the end date for the first time period in the Available To field.

8. Select the Units field.

9. Enter the units available for the resource during the specified time frame.

10. Continue to specify the resource’s availability as necessary.

11. Select

.