Project 2016 - Introduction
Project 2016
Lesson – Working with Calendars
7. Select
.
Step-by-Step
Assign a base calendar to resources.
If necessary, switch to the Gantt Chart view.
Scroll as necessary to view the task bar for the 19 Install Roof task. Point to the Gantt bar to view the end date for the task and notice that it is scheduled to end on Fri 8/31/2018. Switch to the Resource Usage view.
Steps
Practice Data
1. Double-click the resource to which you want to assign a new base calendar. The Resource Information dialog box appears.
Double-click the 8 Roofer resource.
2. Select the General tab
Select
.
3. Select the Change Working Time button .
Click
The Change Working Time dialog box appears.
4. Select the Base calendar list.
Click Base calendar
A list of available base calendars appears.
5. Select the desired base calendar.
Click Site Workers1
The selected base calendar appears in the Base calendar field.
6. Select OK .
Click
The Details dialog box closes.
7. Select OK .
Click
The Resource Information dialog box closes and the base calendar is assigned to the resource.