Project 2016 - Introduction

Lesson – Working with Calendars

Project 2016

Switch to the Gantt Chart view and point to the task bar for the 19 Install Roof task again. Notice that the Install Roof task, to which the Roofer resource is assigned, is now scheduled to end on Fri 8/31/18 . The change occurred since the week of September 3-7, 2018 is nonworking time on the Site Workers1 base calendar. Note other tasks for the project will still occur.

Practice the Concept: Assign the Site Worker 1 base calendar to the 1 Laborer resource.

A SSIGNING A B ASE C ALENDAR TO A P ROJECT

Discussion

If the default project calendar does not meet the needs of your project, create a new project calendar. To create a new project calendar, you need to create a base calendar to reflect working and nonworking time specific to your project. Then, you need to assign the new base calendar to your project using the Project Information dialog box.

If you need to use a new project calendar, you should do so before you enter project information.

NOTE

To see the non-working time on the Gantt Chart change the calendar assigned to non-working time. Double-click the timescale in the Gantt chart. Select the Non-Working Time tab and select the new project calendar.

Procedures

1. Select the Project ribbon.

2. Select the

button.

3. Select the Calendar list.

4. Select the calendar you want to assign to the project.