Project 2016 - Introduction
Project 2016
Lesson – Working with Calendars
5. Select
.
Step-by-Step
Assign a base calendar to a project.
Steps
Practice Data
1. Select the Project tab.
Click
.
The Project ribbon appears.
2. Select the Project Information command.
The Project Information dialog box opens.
Click
3. Select the Calendar list.
Click Calendar
A list of available calendars appears.
4. Select the calendar you want to assign to the project. The selected calendar appears in the Calendar field.
Click Site Workers1
5. Select OK .
Click
The Project Information dialog box closes and the base calendar is assigned to the project.
Open the Change Working Time dialog box and notice that Site Workers1 (Project Calendar) appears in the For calendar box. Cancel the dialog box. Note that the September 3-7 is still displayed as working time
NOTE Assign a project calendar in the Timescale feature. In the View tab, launch the Timescale dialog box. Select the Non- working Time tab. In the calendar field, select the appropriate project calendar.
Practice the Concept: Open the Project Information dialog box and change the project calendar back to the Standard calendar.