Project 2016 - Introduction

Lesson – Learning Project Basics

Project 2016

Procedures

1. Select the Project tab on the Ribbon.

2. Click the

icon in the Properties group.

3. Click the

tab.

4. Click the button. 5. Make any necessary changes in the Details dialog box.

6. Select the desired options and select

.

7. Select

.

Step-by-Step

We will change the working times to 9:00 AM to 6:00 PM, with one hour for lunch.

From the Student Data directory, open HOUSE1.MPP.

Define the project working times.

Steps

Practice Data

1. Click the Change Working Time icon in the Project tab. The Change Working Times dialog box appears.

Click

.

2. Select the Work Weeks tab.

Click

.

A list of base calendars appears.

3. Select the Details button.

Click

.

The Details for dialog box appears.

4. Select the Day(s) to change. The desired days are selected.

Select Monday, hold down [Shift] then click Friday.