Project 2016 - Introduction

Project 2016

Lesson – Learning Project Basics

Steps

Practice Data

5. To change the working hours, select the Set day(s) to these specific working times: The option is selected. 6. Click in a cell to type a new start time. The cell is selected.

Click Set day(s) to these specific working times:

Click the first cell in the From column. Type 9:00 AM and press the right arrow key. Type 1:00 PM in the corresponding To box and click in the From box on the second line. Type 2:00 PM and press the right arrow key.

7. Type the desired time.

Type the desired start time.

8. Type the desired end time. Type desired end time.

9. Set the desired time in the From column. Type desired start time for the afternoon.

10. Enter the desired End time. The desired end time is set.

Type 6:00 PM and press the [Enter] key.

11. Select OK .

Click

.

The dialog box closes, and the options are saved.

12. Select OK .

Click

.

The Change Working Time dialog box closes, and the options are saved.

A DDING A N ONWORKING D AY

Discussion

By default, the project calendar defines the standard working days (Monday through Friday) and nonworking days (Saturday and Sunday) for a project. The default calendar has no holidays, so you must mark the appropriate holidays as nonworking days. It is very important to mark all applicable nonworking days as durations are calculated according to this calendar. In any view, nonworking days are identified with gray shading.

OFFICEPRO, Inc.

Page 27