Project 2016 - Introduction
Lesson – Learning Project Basics
Project 2016
You can enter the nonworking days by directly opening the Change Working Time dialog box.
The Change Working Time dialog box
NOTE To mark multiple days in the currently displayed calendar at the same time, drag to select consecutive days. To select non- consecutive days, hold the [Ctrl] key, click the desired days, and then release the [Ctrl] key.
Procedures
1. Select the Project tab on the Ribbon.
2. In the Properties group, click . 3. Display the month in the calendar in which you want to add the nonworking day. 4. Select the day on the calendar you want to add as nonworking. 5. In the Exceptions tab, type the name of the holiday. 6. Press the tab key. The selected day from the calendar is automatically added. Change the date manually, if needed 7. Select OK .
Page 28