Project 2016 - Introduction

Project 2016

Lesson – Organizing Tasks

Steps

Practice Data

1. Select the ID number for the row containing the task you want to move. The entire row is selected and the mouse pointer changes into an arrow. 2. Drag the task ID number to the new position.

Click ID number 8 for the Select Subcontractors task.

Drag task ID number 8 until the shadow line is between the 6 Obtain Bids and 7 Complete Planning Phase tasks.

A shadow line indicates the task position as you drag, and then the task moves to the new location.

D OCUMENTING A T ASK

Discussion

Create notes for tasks when you want to document additional task information. When a task contains a note, a Notes icon appears in the Indicators column. Pointing to the icon displays a ScreenTip with the note text.

Task notes are recorded in the Task Information dialog box Notes page. The Task Information dialog box contains the scheduling and resource information for a task. When entering notes, you can format the font and text alignment, create a bulleted list, or insert a picture.

Adding a task note