Project 2016 - Introduction

Lesson – Scheduling Tasks

Project 2016

The Task Dependency dialog box

Procedures

1. Switch to the Gantt Chart view. 2. Point to the link line joining the tasks for which you want to change the relationship type. 3. Double-click the link line between the two tasks. 4. Select the Type list. 5. Select the desired type of relationship.

6. Select

.

Step-by-Step

Change task relationships.

Display the Gantt bar for the 4 Draft Proposal task. View the link line between the 4 Draft Proposal and 5 Request Bids tasks.

Steps

Practice Data

1. Point to the link line joining the tasks with the relationship type you want to change. A ScreenTip appears and displays information about the task relationship.

Point to the link line joining the 4 Draft Proposal and 5 Request Bids tasks.