Project 2016 - Introduction
Lesson – Scheduling Tasks
Project 2016
If you insert a task between two linked tasks that have a lag or lead time, the newly inserted task is not linked.
Lead and lag time are both entered in the same field. Enter lag time as a positive number, including the unit of duration. If you do not enter a unit of duration, the default duration of days is entered. For example, you enter 2d for two days of lag time. Lead time is entered as a negative number. For example, -2d means that the task can start two days before the predecessor task is finished. You can also enter lag and lead time as percentages, such as 50% for lag time and -50% for lead time.
Viewing lag time between tasks
Procedures
1. Switch to the Gantt Chart view. 2. Double-click the link line between the tasks for which you want to enter a lag or lead time. 3. Enter the desired lag or lead time in the Lag spin box.
4. Select
.
Step-by-Step
Apply lag and lead time.
We will apply a lag of two days to allow the concrete foundation to cure. Scroll as necessary and view the link line between the 10 Build Foundation and 13 Construct Frame summary tasks.