Lesson – Tracking Your Progress

Project 2016

Tasks dialog box to enter the percent of work complete. When entering completion percentages, you can either type the value or use the corresponding spin box.

The Update Tasks dialog box

NOTE

You can also enter a completion percentage for a task on the General page of the Task Information dialog box.

Procedures

1. Display the Tracking table in the Gantt Chart view or, from the View tab, Split View group, click the Details check box and select Task Form to track progress by entering the percentage of work complete. 2. To use a table to enter the percentage of work complete, select the % Complete field for the desired task from the Tracking table. 3. Type the desired value. 4. Press [Enter] . 5. To enter a percentage using the Update Tasks dialog box, select the task you want to update. 6. Click the Update Tasks button on the Task ribbon, Schedule group. 7. Enter the actual percentage of work completed in the % Complete field.

8. Select

.

Step-by-Step

Enter the percent complete.