Project 2016 Intermediate

Project 2016

Lesson – Tracking Your Progress

Display the Tracking table fields. Drag the split bar all the way to the right to display the % Complete field.

Enter a status date for the project of 7/25/18 in Project Information .

Steps

Practice Data

1. To use the table to enter the

Click in the % Complete field.

percentage of work complete, for the 10 Select Subcontractors task select the % Complete field for the a task. The field is selected.

Type 65.

2. Type the a value.

The value appears in the % Complete field.

3. Press [Enter] .

Press [Enter].

The progress information is updated.

4. To enter a percentage using the Update Tasks dialog box, select the task you want to update. The task is selected. 5. On the Task ribbon in the Schedule group click the Mark on Track drop- down menu. The drop-down menu appears. The Update Tasks dialog box opens with the value in the % Complete field selected. 7. Enter the actual percentage of work completed in the % Complete field. The percentage appears in the % Complete field. 6. Select Update Task

Click the 10 Select Subcontractors task.

Click

.

Click

.

Select 80%.

8. Select OK .

Click

.

The Update Tasks dialog box closes and the percent complete for the task is updated.