Lesson – Tracking Your Progress
3. To enter actual work completed, select the Actual field for the task or for the individual resource assigned to the task you want to update. 4. Enter the total hours of work completed on the task or the hours of work completed by the individual resource. 5. Press [Enter] . 6. To enter the remaining work, select the Remaining field for the task or for the individual resource assigned to the task you want to update. 7. Enter the total number of hours of work completed on the task or the hours of work completed by the individual resource. 8. Press [Enter] .
Step-by-Step
Enter completed and remaining work values.
Switch to the Task Usage view, apply the Work table, and drag the split bar as far right as possible. Double-click the right border of the Task Name column to view the entire field.
For 10 Select Subcontractors task, the Superintendent has performed a total of 32 hours of work. However, due to a scheduling problem, you need to schedule this resource to perform 12 more hours of work that was originally scheduled for the Superintendent resource.
Steps
Practice Data
1. For the 10 Select Subcontractors task, select the Actual field for the task or for the individual resource assigned to the task you want to update. The desired Actual field is selected. completed on the task or the hours of work completed by the individual resource. The total number of hours of work completed is entered. 2. Enter the total hours of work
For the Superintendent, click the Actual field .
Type 44.
3. Press [Enter] .
Press [Enter].
The appropriate fields are updated.